Thursday, 3 July 2014

Week 21- further work inside and out



Hello all,

Almost a month since our last post; where has the time gone?! Since the last post a lot of work has taken place inside the Mill as well as some works outside. We now have a water supply thanks to the installation of a borehole and the first lot of bespoke windows have arrived, but most importantly we can now go up and down between the floors via the temporary stairs which have been put in as the landings are now complete....exciting!

Graham the builder with the plasterboard
pipe work for heating, water etc 
pipe work goes in along the kitchen floor
plasterboard ready to go up in our bedroom
the borehole going in 
starting the drilling for the borehole
Electrician Henry Pring in the kitchen
the sewage treatment plant going in!



the digger starting work on the drainage at the back of the barns



the poop plant arriving- thanks WCI Ltd
Temporary stairs until the proper ones arrive!

                                        View up the stairs from hallway 

post sandblasting in the kitchen to clean the stone
7 bespoke windows for the gable end in the workshop
studwork in the kitchen finally completed and ready for insulation

Aquaboard going up in one of the bathrooms!