As we entered week 3 the weather turned (gee whiz we Brits are for ever talking about the bloody weather!!) this time for the better. The pump went into action and the builders finished off the footings and block work for the sitting room. The final 2 concrete lorries arrived and 3 weeks and 2 days into the build the concrete floor slabs were complete.
 |