Monday, 29 September 2014

September Update - Nearly There

We are moving forward on the project.  With the underfloor heating installed we have been able to bring in the screeding company.  We are now well into the second fix and have set our sights on moving in within a month or so.

Screeding lorry


Screeding in the utility

and in the sitting room

Tiling in the guest room en-suite
 The tilers have also arrived on site and within a week the bathrooms in the guest room and our room are complete ready for the plumbers to come into second fix.
Tiling in out en-suite
 With the Mill being over three stories we have had to fire proof the doors to comply with building regs.
Second coat of fire proofing

Painting in the Kitchen is complete

Painting is complete in the hallway and the roof light has been cleaned up inside

View out from the hallway

Bedroom 2 painting complete
 The biomass providers South West Renewable have begun the installation of the biomass system
Boiler room

Painting in our bedroom complete

And the tiling in the en-suite complete

First coat of paint in the sitting room done